Phase 2B – Glenwood Lane to Ransom Drive underway

Phase 2B – Glenwood Lane to Ransom Drive:

Traffic is transitioned to the existing right shoulder for Phase 2B construction operations. Work to be expected in this phase includes water line relocations, sewer line relocations, drainage structure installation, and roadway build-up and widening.

View all phases of Section One – Shady Spring to Beaver.

Categories Construction

Phase 2A – Rt. 3 and Rt. 19 Intersection to Glenwood Lane underway

Phase 2A – Rt. 3 and Rt. 19 Intersection to Glenwood Lane:

Traffic is transitioned to the existing left shoulder for Phase 2A construction operations. Work to be expected in this phase includes water line relocations, sewer line relocations, drainage structure installation, and roadway build-up and widening. 

View all phases of Section One – Shady Spring to Beaver.

Categories Construction

Relocation of utilities from Rt. 3 to Beaver ongoing during Section One

Relocation of utilities from Rt. 3 to Beaver:

During the duration of Section One, relocation of utilities are ongoing throughout the entire project area and in some cases beyond the project limits. Overhead line work and pole relocations are taking place from Rt. 3 working toward Beaver currently.

Mountaineer Gas is operating from Rt. 3 toward Beaver relocating underground gas lines with drilling and trenching operations in various locations.

Expect delays and temporary work zone setups throughout the duration of these relocations. Exercise caution through these work zones, expect delays, and in some events stopped traffic.  

View all phases of Section One – Shady Spring to Beaver.